- 01
Prepare the substrate
Clean and degrease tiles, plaster or concrete. Repair cracks. Sand glossy surfaces lightly. Apply our bonding primer and let cure for 4 hours.
- 02
Apply Microbase (2 coats)
Trowel the first Microbase coat with fibre mesh. Let dry 12 hours, sand smooth. Apply the second Microbase coat. Sand again.
- 03
Apply Microfinishing or Microtraffic (2 coats)
Apply your chosen finish coat thinly with a steel trowel. Let dry 6–12 hours between coats. Sand lightly between coats.
- 04
Seal
Roll on the first coat of 2-component polyurethane sealer. Wait 4 hours. Apply the second sealer coat. Cure 24 hours before light use, 7 days before heavy traffic or water exposure.