How to apply microcement.

Four stages, from substrate preparation to sealing. Read the full method below or download our PDF after checkout.

  1. 01

    Prepare the substrate

    Clean and degrease tiles, plaster or concrete. Repair cracks. Sand glossy surfaces lightly. Apply our bonding primer and allow approximately 1 hour to dry.

  2. 02

    Apply Microbase (3 coats on walls and floors)

    Mix Microbase with Royal Resin at 4.5 L per 10 kg of powder. Apply Microbase with a trowel. Wet on dry: allow about 3 hours and sand lightly before the next coat. Always apply 3 coats on walls and floors, maximum 1 mm per coat. Embed 50 g fibreglass mesh in the fresh base coat; it is mandatory on floors. Consumption: ≈2.0 kg/m² in total for the 3 coats — one 20 kg bucket per 10 m².

  3. 03

    Apply Microfinishing or Microtraffic (2 coats)

    Apply your chosen finish coat thinly with a steel trowel. Wet on dry: allow about 3 hours and sand lightly before the next coat. Use Microfinishing on walls only (15 kg bucket; 0.5 kg/m² for 2 coats), or Microtraffic on floors (18 kg bucket; 0.95 kg/m² for 2 coats).

  4. 04

    Seal

    Roll on the first coat of 2-component polyurethane sealer. Allow 8 hours to 2 days between coats. Apply the second sealer coat. Follow the technical data sheet for curing and use.

Before you order, work out the quantity with the microcement calculator — coverage per coat, kits needed and the 10% wastage allowance, all in one place. For coverage rates, drying times and performance data, see the technical data sheets. For general questions before ordering, read our microcement FAQs.

Applying it for a living? Apply for a KCBerry trade account. Writing it into a drawing set? See how to specify microcement.

Buy the kit, apply it yourself.

Every KCBerry kit includes everything you need plus printed instructions.